I would like to have the wood furnace fully functional by the end of January.
Saturday, December 19, 2009
Years End
I would like to have the wood furnace fully functional by the end of January.
Sunday, November 8, 2009
November - week one
Tuesday, October 27, 2009
October
Wednesday, September 23, 2009
More Progress
Monday, September 7, 2009
All framed in
Monday, August 24, 2009
Movin' On Up...
With the blessing of mother nature, it won't rain till end of week and we can have a completed roof!! That would be the most awesome thing ever!
It has been amazing to watch the house change in proportion with every wall and floor put in place! There were days that I thought 'wow this doesn't look all that big,' and then there were others I'd look at John and say 'what did we do?' For some reason no mater how much you think you know spacially what it will look like, it always looks just fine on paper.
I'm still hoping to be in late fall. Thanksgiving would be great!
The windows, doors and siding will be next after the roof. Then the interior work begins.
This has been a learning process. If we were to do this again I know there are some things that we could/would do differently...maybe we'll turn that into a book. The experience thus far though has not been as bad a a lot of people made it out to be, but I won't discount their advice since we are still in process and anything , can happen.
Monday, August 3, 2009
ON AND ON
Tuesday, July 14, 2009
Framing Update
Sunday, June 28, 2009
Framing starts!
Wednesday, June 3, 2009
Lumber arrives
Thursday, May 28, 2009
May showers....
The gravel was brought into the foundation and graded so that the floor is an even four inches. Once that is done, they lay black plastic down with wire mesh and rebar on top. Finally, the cement truck comes in and they pour a section. So far we have two sections done and the final one should be completed tomorrow. The last thing will be to pour cement in the block on the back wall every four feet with rebar per code as reinforcement, then the cap blocks go on. When that is done, hopefully by early next week, we can start on the framing.
Sunday, May 3, 2009
And the Rain Continues...
The footer took the guys all of 2 hours to get it poured and smoothed out. John's help was also enlisted to wheel over loads where the truck couldn't reach. There are 14 1/2 yards of cement that make up the footer. The front of the house is about 18" thick, while the sides are about 10"...I don't think she'll move.
So once that was poured, it then poured rain for about 4 days...then the heavens managed to dry up for a few days and the guys laid the block. There are 2100, 10" cinder blocks that make up the basement.
Minto, now thinks it's his. He's always going in and out of the basement door opening. He likes to yodel at John and I. Once it echo's he stops looks around and starts all over again.
The next step is to get the floor poured but it hasn't stopped raining long enough for that to happen. Hopefully in the next week or so, the heavens will once again dry up and allow us to proceed.
Sunday, March 29, 2009
Rainy Days
At our request, while they were digging, they took out another half dozen trees so we have been working on getting them cut up and stacked. Going slowly but getting there.Not sure what this week will bring as the weather is not looking good, at least the first couple of days. The builder was working on getting the block ordered, getting rebar and lining up the cement trucks - he is planning on pouring the footer this week if he can. The earth work guys are almost done with the initial work. They need to dig a trench from the corner of the house out over the hill side for drainage, finish the trench for water line and touch up the driveway. They are going to bring in some more gravel and once that is done, we will be ready for the first draw from the bank.
Hopefully the weather will cooperate this week...Will update again in a week or so.